Heating Plant C.Budejovice
Modernization of the boiler control system for boilers K9, K10, K11, K12, TUV K9,K10, TUV K11,K12
Client: Heating Station C.Budejovice
Location: Ceske Budejovice
Project description
ZPA Industry provided during 1993 – 2000 modernization of the boiler control system for boilers K9, K10, K11, K12, TUV K9,K10, TUV K11,K12. Company provided complete engineering including project design, procurement and deliveries, assembly, technical documentation, project state documentation and operator and maintenance personnel training. Company further provided complete deliveries and works on electrical systems including equipment for given technology section. GE Fanuc Series 90-30 was integrated as the control system. For process control and visualization company implemented CIMPLICITY HMI software. Application software has graphical displays for control of technological units, sequential programs, control loops, alarm functions, historical functions and trends, reports. Scope of delivery included:
o Project engineering
o Partial modification of high voltage distribution and control cabinets
o Control system
o Project commissioning
o Operator and maintenence personnel training
Technology description
Project: Boiler K9
Project description :
Complete control system reconstruction incl. control of heavy oil burners and sequantial automatic drive control – complete field instrumentation, electrical system
Parameters: Steam output 75 t/h.
T output steam 540 st.C
P output steam 13,9 MPa
Project: Boiler K10
Project description:
Complete control system reconstruction incl. control of heavy oil burners and sequantial automatic drive control – complete field instrumentation, electrical system
Parameters: Steam output 75 t/h.
T output steam 540 st.C
P output steam 13,9 MPa
Project: Water heat treatment for K9 and K10
Project description:
Complete control system reconstruction complete field instrumentation, electrical system for machinery of K9, K10 - feeders 1, 2, 3
Project: Boiler K10 K11
Project description:
GO of control system – all control loops incl. output power, burning, feeder – complete field instrumentation
Parameters: Steam output 125 t/h.
T output steam 540 st.C
P output steam 13,9 MPa
Fuel – brown coal, 4x mill
2x stabilizing gas burner
Project: Boiler K12
Project description:
Complete reconstruction of control system incl. control of gas burners and seq.aut. drive control
Parameters: Steam output 160 t/h.
T output steam 540 st.C
P output steam 13,9 MPa
Fuel – brown coal, 4x mill
2x stabilizing gas burner
Project: Water heat treatment for K11 and K12
Project description:
Complete control system reconstruction complete field instrumentation, electrical system for machinery of K11, K12 - feeders 4, 5, 6.
Dates of commissioning:
1998-2000